Projects

This turnkey contract for the project awarded to Venergy demonstrates the team’s design, engineering, construction and O&M experience relating to the installation of Solar PV systems in tropical island environments and hurricane winds, as well as, on federal VA facilities. The solar system required a 480V net metered interconnection with the interconnection agreement with Hawaii Electric Co.

Venergy Group was selected by the University of Central Florida to retrofit all of their fluorescent lights with LED, energy saving bulbs. Upon completing the required task with amazing success and days before the deadline, Venergy was rewarded with multi buildings based on UCF budget and timing to do the same. The scope of work has ranged from simple LED retrofit and ballast removal, electrical repairs where needed, as well as fluorescent replacement. Currently Venergy has over 7 UCF building awaiting LED retrofit.

Venergy Group was awarded with the contract for the installation of the methane collection and venting system at the greystar Davie II Apartment Complex. Over time, methane gas can build up under buildings causing a big problem if it came into contact with a spark or flame. Venergy installed a system to collect and vent off this gas so it doesnt become an issue. To accomplish this, the following work was done: installation of 4 in. diameter HDPE perforated pipe, cutting trench of approximately 4 in. width by 4 ft depth at trench locations.

Retrofit over 7000+ LED bulbs of various types and sizes for six buildings and parking lots totalling over 180,000+ sq/ft of space(excludes parking space size), replacing 47 tons of cooling capacity with new units with better energy efficiency for two building totalling over 29,000+ sq/ft of space, the installation of commercial grade UV lighting for 22 HVAC units, and energy saving smart thermostats for 22 HVAC units that cover 49,000+ sq/ft of space.

Venergy was selected to take on the task of running 700' of underground electrical utilities from a service transformer to a newly built camp site shower house. Three 700 mcm alumium conductors and a 3/0 copper ground conductor where ran through 4" PVC schedule 40 conduit, and connected with insulated multitap connectors, with 3M detectable buried tape. A new 400 amp service panel was installed replacing the previous aged 200 amp service disconnect.

Venergy Group was selected by the Department of Veterans Affairs to restore the Domiciliary at the Lake Nona VA Medical Center in Orlando, FL after it sustained considerable damage from a fire.  Scope of work included the repair of drywall, ceiling tile, flooring, cabinets, appliances, interior lighting fixtures and electrical receptacles.  In addition to the flooring on all four floors, Venergy also remediated smoke damage to walls by cleaning and repainting.  All furniture affected by the fire and subsequent flooding from the fire alarm sprinkler system was replaced along with all applian

Venergy Group was selected by the federal government to complete the removal and installation of the roof and all rooftop mechanical equipment at the National Hurricane Center in Miami, FL.  The existing built-up gravel roof was removed completely down to the concrete substrate and a new PVC membrane roof was installed.  Three 60 ton rooftop condensing units were removed from the roof via crane and replaced with new units on engineered, stainless steel curbs.  Evaporator coils, piping and controls were all replaced and recalibrated.  In addition to the roofing and mechanical work, Venergy a

United States Department of Agriculture - Agricultural Research Service Western Human Nutrition Research Center in Davis, CA.  REPLACE EXISTING POLE AND BOLLARD LIGHT FIXTURES WITH LED LIGHT FIXTURES’.  Installed replacement LED lighting at the USDA Site in Davis, CA

Venergy was selected to provide this project due to its experience in solar (PV) design and implementation along with experience domestically and abroad. Venergy has been awarded as EPC to design a turnkey Solar Photovoltaic (PV) System Installation at the VA Medical Center (VAMC) at the Community Based Outpatient Clinic (CBOC) Building located at 498 Chalan PalaV) Design, Engineering, Permitting, Project Management, Construction Management, Installation and Commissioning of the solar array.

Venergy installed an AutoTune (Power Factor Correction) device at the main switchgear of the manufacturing plant with sensors and an advanced meter that was then connected to the current Industrial Control System (ICS). Venergy identified and initiated this plant energy reduction project and then designed, installed, and commissioned the project. Following staff training and implementation, this new energy project reduced energy consumption by 6% and eliminated a power factor penalty of 3%. Overall payback for the customer was under 12 months.

Started in 1956, Jersey Mike’s now has 1,300 restaurants open and under development nationwide.  In just three years, the company has nearly doubled in size.  Venergy Group will provide labor and materials under the scope of work for a new location in Boynton Beach, FL.

Scope of Work:

  1. Furnish all permits and inspections
  2. Furnish and install one 6-ton carrier package unit and one 3-ton carrier split system condenser in addition to Airhandler.
  3. Furnish and install all supply and return ductwork per plans
  4. Furnish and install all supply return and return grilles per plans
  5. Modify existing ductwork on 2 existing 3.5-ton air handling units
  6. Furnish and install bathroom exhaust fans per plans
  7. Furnish and install thermostats per plans
  8. Install owner provided kitchen hood and heat hood exhaust and make up air fans per plans
  9. Furnish test and balance reports per plans
  10. Furnish and install duct detectors with remote key stations per plans
  11. Furnish and install low voltage wiring for control and universal shut down per code
  12. Furnish and install numbering for RTU per plans
  13. Furnish and install condensate drains and refrigerant line sets
  14. Insulate refrigerant and condensate lines

Miami Roofing/HVAC - Venergy Group was selected by the federal government to complete the removal and installation of the roof and all rooftop mechanical equipment at the National Hurricane Center in Miami, FL.  The existing built-up gravel roof was removed completely down to the concrete substrate and a new PVC membrane roof was installed.  Three 60 ton rooftop condensing units were removed from the roof via crane and replaced with new units on engineered, stainless steel curbs.  Evaporator coils, piping and controls were all replaced and recalibrated.  In addition to the roofing and mechanical work, Venergy also renovated all existing electrical conduits and cabling on the rooftop, installing new raised, rigid galvanized conduits and providing additional weatherproofing measures to pre-existing antennas and satellites on the rooftop.  Lightning protection system was replaced along with all edge metal and coping.  Parapet walls were resurfaced and waterproofed.

Venergy performed as sub-contractor and  assisted Alares, LLC (SDVOSB) in conducting Level II ASHRAE Audits for Department of  Veteran Affairs  buildings

Venergy furnished all engineering, design, and placed into service an advanced electrical metering system with future capabilities to add water, natural gas, and steam metering system with future control points to monitor lighting and HVAC. The equipment provided includes: AcquiSuite Data Acquisition Server (DAS); Modhopper wireless 900 MHz encrypted secure transceivers by Obvius to transmit the data; Veris E50C2 power quality meters (Modbus/Bacnet); Custom built Dell energy management computer.

Venergy redesigned and repaired Energy Management  Control Systems (EMCS) (i.e. Advanced Metering) for 135 buildings ranging from 1,920sq ft. to  287,920sq ft. Redesign and expanded Wifi communications backbone, installation of water and electric meter infrastructure. Integration of all metering and control systems into SCADA   software using both Wonderware and LonWorks including, air quality controls systems, HVAC,  Street lighting, Diesel fuel, back up generators electrical and water meters. Main data central  operations system relocation and back-up data central operations system.Test, commission,  and train personnel.

Preliminary assessment of buildings  within  contract in order to develop ECMs for the Investment Grade Audit. Together with SAIC’s   guidance, Venergy will provide Project Management of all ECMs; Advanced metering design,  install  and  commissioning; Energy Management Control System design, install and  commissioning.  HVAC design, installation, commissioning and maintenance; Solar design,  install and commissioning; lighting design and installation; building envelope upgrades;    Operations &  Maintenance throughout ESPC contract life cycle and Measurement and  Verification assistance

Venergy provided and installed Power  Factor Correction and Voltage Control Guard (VCG) units which will assist the Texas National  Guard to meet their energy reduction goals/mandates. During the measurement and  verification  process of the VCG the Texas Army National Guard realized an 18% reduction in  kW h at the sub-panels where the VCG was connected.  This resulted in  less than an 18  month Return On Investment (ROI). The PFC Unit  completely eliminated  the demand charge  which resulted in $700 per month savings capturing less then an 18 month ROI.

Texas Army National Guard Camp Swift

Venergy procured, designed, project  managed, site-supervised, installed and commissioned a solar array in order to provide off-  grid lighting to a canopy for the Texas Army National Guard at Camp Swift Training Site.

  • Solar Module:  2 Astronergy 255 watt Module Silver MC4 CHSM6610P-255 - 40mm Frame
  • Batteries:  WSS Battery Bank UPG 400aH @ 12VDC 4,800 watt hours (4) 6V Batteries
  • Controller:  Outback FlexMax FM60, 60 amp, Charge Controller
  • Lights:  2 50W Flood Light  12V DC LED

Connecticut Air National Guard

Venergy furnished all project management,  engineering, labor, materials and equipment to design, install, test and commission an  Advanced Metering System for the Bradley Air National Guard (ANG) in Orange, CT - Air  Control Squadron  to make their existing system 100% compliant with their  current CTANG DDC System.  System components included radio communication via  wireless IP Radio Network, metering and tying into the EMCS system.

Michigan Air National Guard

Venergy provided 165 High Bay Induction Lights and Light Cords with Caps to the Selfridge Air National Guard Base in Michigan.

Our Mission

To assist each and every client in meeting and exceeding their energy goals by providing a veteran-based, one-stop shop with turn-key energy solutions executed with Honor, Duty and Integrity.


We have a friendly and knowlegable staff happy to take your call:

866-977-7555